A) 60
B) 45
C) 40
D) 30
Using Flip rule:
A and B complete work in = 15 days
One day’s work of (A + B) = 1/15
B complete the work in = 20 days;
One day’s work of B = 1/20
Then, A’s one day’s work
=1/15−1/20 = ( 6-5)/60= 1/60
Thus, A can complete the work in = 60 days.