A) 3 hours
B) 6 hours
C) 5 hours
I compete the task in = 20 hours
4 people join with the same efficiency
So,
The total persons working now
= (Me + 4 people)
= (1+4)
= 5
Now,
1 people can finish in = 20 hours
5 people can finish in = 20/5 = 4 hours